Citywide Ballfield Lighting Installation (CNYG-2815M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install energy efficient ballfield lighting retrofits at various parks facilities citywide.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: March 2015
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: June 2016

Construction

Start Date: September 2016
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,460,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/16/2017