Citywide Energy Efficient Ballfield Lighting Retrofits (CNYG-2915M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct energy efficient ballfield lighting retrofits.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: February 2015
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2019
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $4,970,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/26/2020