Citywide Energy Efficient Ballfield Lighting Retrofits (CNYG-2915M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    99% complete

This project will construct energy efficient ballfield lighting retrofits.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: February 2015
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $4,969,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/29/2020