Sunset Cove Park Saltwater Marsh and Coastal Upland Construction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct a salt marsh and upland coastal forest area in Sunset Cove Park.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: November 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Adjusted Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Private

Location

south of West 19th street between Jamaica Bay and Cross Bay Boulevard

Project Staff

Contact NYC Parks about this project

Last updated: 02/16/2018