Prospect Park Long Meadow Ballfields 4 and 5 Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

Work to include the renovation and maintenance of turf Ball fields Number Four and Five, work to include seeding, drainage, site work, and fence repairs.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Adjusted Completion Date: February 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Prospect Park, Brooklyn
Prospect Park - Long Meadow is located along the western edge of park bordering Prospect Park West, and Prospect Park Southwest along the southern border. Long Meadow bounds south and east portion of West Drive

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/23/2018

Was this information helpful?