Prospect Park Internal Pathways Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct three existing pedestrian pathways with flooding, drainage and erosion issues.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: April 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: March 2017

Construction

Start Date: May 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $269,000
Funding Sources:
  • Borough President
  • City Council

Location

Prospect Park , Brooklyn
Lake Path near Parkside Drive; Endale Arch near Flatbush and Prospect Park West; Litchfield Villa Parking Lot, near Prospect Park West and internal road West Drive.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/20/2018