Parade Ground Ballfield 7 Reconstruction and Adult Fitness Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    77% complete

This project will construct seven new adult fitness equipment stations, a misting station, trees and benches, and reconstruct the synthetic turf field at Ballfield 7 at the Parade Ground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: June 2015
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: July 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $629,000
Funding Source: City Council

Location

Parade Ground , Brooklyn
Near Caton Avenue and Stratford Road

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/15/2018