Clement Clarke Moore Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Clement Clarke Moore Park.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: January 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $1,514,000
Funding Sources:
  • Mayoral
  • City Council

Location

Clement Clarke Moore Park , Manhattan
10th Avenue between West 21st Street and West 22nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/20/2019