NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Brower Park Skate Park Element Installation

  • Design
    100 % complete 
  • Procurement
    100% complete  
  • Construction
    100% complete  

This project will construct new skate park elements.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: June 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: November 2015

Construction

Start Date: April 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $49,000
Funding Sources:
  • Mayor
  • Borough President

Location

Brower Park , Brooklyn
Brower Park; bounded by Brooklyn Avenue, Park Place and Kingston Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/28/2017

Was this information helpful?