NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

St. Mary's Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    72% complete

This project will construct new play equipment, benches, and pavements at St. Mary's Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2014
Projected Completion Date: June 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $1,491,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

St. Mary's Park, Brooklyn
Huntington Street and Smith Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/16/2018

Was this information helpful?