Henry Hudson Park Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    10% complete

This project will reconstruct the basketball and handball courts at Henry Hudson Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: August 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $2,049,000
Funding Sources:
  • City Council
  • State

Location

Henry Hudson Park , Bronx
Kappock Street between Independence Avenue and Palisade Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2018