Williamsbridge Oval Skate Park Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a new skate park at Williamsbridge Oval.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: March 2017
Adjusted Completion Date: November 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Williamsbridge Oval, Bronx
Reservoir Oval East between Holt Place and Reservoir Place in Williamsbridge Oval

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2017