Shore Road Park Steel Fence Installation, Vegetation Removal and Erosion Control

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct steel fencing, clear vegetation, and control erosion at Shore Road Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: June 2015
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,724,000
Funding Sources:
  • Mayoral
  • State

Location

Shore Park and Parkway , Brooklyn
Shore Road between 3rd Avenue and 95th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2018