Tompkins Square Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    25% complete

This project will reconstruct two playgrounds in Tompkins Square Park with new play equipment, safety surfacing, spray showers, seating, and fencing.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: February 2018
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $2,296,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Tompkins Square Park , Manhattan
East 7th Street and Avenue B

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project