Spring Street Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    79% complete

This project will reconstruct Spring Street Park (Soho Square).

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $3,790,000
Funding Sources:
  • City Council
  • Private

Location

Spring Street Park , Manhattan
6th Avenue betwen Spring Street and Broome Street.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/20/2018