Green Central Knoll Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new comfort station and an accessible ramp in Green Central Knoll.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: October 2015
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $3,793,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Green Central Knoll , Brooklyn
Evergreen Avenue, Noll Street, Central Avenue, Flushing Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/21/2020