Green Central Knoll Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    67% complete

This project will construct a new comfort station and an accessible ramp in Green Central Knoll.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: October 2015
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Adjusted Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $2,898,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Green Central Knoll , Brooklyn
Evergreen Avenue and Knoll Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/14/2018