NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Dome Playground Sport Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will reconstruct the basketball & handball courts located in Dome Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: November 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $1,342,000
Funding Sources:
  • Mayoral
  • City Council

Location

Dome Playground, Brooklyn
Dahill Road & 38th Street, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?