Bildersee Playground Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct a playground, spray shower, landscaping, benches, and storm water improvements. Work may be completed in two phases pending project funding. Phase One: basketball, track, synthetic field, play area, landscaping and seating Phase Two: Two age specific play structures, spray shower, adult fitness, landscaping and seating.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bildersee Playground, Brooklyn
Southeast side of Flatlands Avenue between East 81st Street and East 82nd Street, next to IS68 Bildersee Middle School.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017