Bildersee Playground Reconstruction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will construct a new synthetic turf field and reconstruct the basketball courts at Bildersee Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $3,241,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bildersee Playground , Brooklyn
Flatlands Avenue between East 81st Street and East 82nd Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/15/2018