Bildersee Playground Reconstruction Phase 1

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct a new synthetic turf field and reconstruct the basketball courts at Bildersee Playground.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Adjusted Completion Date: May 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bildersee Playground , Brooklyn
Flatlands Avenue between East 81st Street and East 82nd Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/23/2018