Evergreen Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will install new playground equipment, pavement, fencing, drainage, site furniture, and lighting.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: February 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Adjusted Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Evergreen Park , Queens
Saint Felix Avenue Between 60th Street and 60th Lane In Evergreen Park Borough of Queens

 