Frank Golden Park Fields Reconstruction Phase II

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will reconstruct the athletic fields and park amenities at Frank Golden Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: December 2019
Projected Completion Date: November 2020
Adjusted Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $4,536,000
Funding Sources:
  • Borough President
  • City Council

Location

Frank Golden Park , Queens
15th Avenue and 132nd Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/27/2020