Park of the Americas Synthetic Turf and Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    91% complete

This project will reconstruct the playground, spray shower and synthetic turf field at Park of the Americas.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $4,600,000
Funding Sources:
  • Mayoral
  • City Council

Location

Park Of The Americas , Queens
41st Avenue, 103rd Street, 42nd Avenue, 104th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/07/2020