Bowne Park Pond Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pond in Bowne Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: August 2016
Adjusted Completion Date: October 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Bowne Park , Queens
Pond in Bowne Park, Bounded by 29th and 32nd Avenues and 155th and 159th Streets

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/24/2018