Briarwood, Phil Rizzuto and Smokey Oval Playgrounds Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This multi-site project will reconstruct pavements, play equipment, fencing, drainage, water service, and general site work in Queens.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: April 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: January 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020