New Dorp Beach Site Restoration in Great Kills Park (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    25% complete

This project will reconstruct Hurricane Sandy-damaged site amenities, a spray shower and paths at New Dorp Beach in Great Kills Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date: May 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: March 2018

Construction

Start Date: April 2018
Projected Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $400,000
Funding Sources:
  • Mayoral
  • Federal

Location

Great Kills Park , Staten Island
New Dorp Beach between Ebbits Avenue and New Dorp Lane along Cedar Grove Avenue, in Great Kills Park

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 10/18/2018