John J Carty Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the tennis courts in John J. Carty Park.

Project Update: Bids have been opened and are being evaluated.

Project Timeline


Start Date: October 2015
Projected Completion Date: September 2016
Completion Date: May 2017


Start Date: May 2017
Projected Completion Date: February 2018
Adjusted Completion Date: July 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council


John J Carty Park , Brooklyn
East side of Fort Hamilton Parkway between Marine Avenue and 101st Street


Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 03/21/2018