John J Carty Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the tennis courts in John J. Carty Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: September 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

John J Carty Park, Brooklyn
East side of Fort Hamilton Parkway between Marine Avenue and 101st Street

 

Project Staff

Project Liaison: Davey Ives