John J Carty Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the tennis courts in John J. Carty Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: September 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,228,000
Funding Sources:
  • Mayoral
  • City Council

Location

John J Carty Park , Brooklyn
East side of Fort Hamilton Parkway between Marine Avenue and 101st Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/17/2018