Flushing Meadows Corona Park Roosevelt Avenue Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Roosevelt Avenue entrance to Flushing Meadows Corona Park.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: January 2017

Construction

Start Date: February 2017
Projected Completion Date: August 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $2,316,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
Roosevelt Avenue between Grand Central Parkway and Long Island Rail Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/18/2018