Queens General Site Work (QG-915M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fencing and drainage systems at various parks in Queens.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: March 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: June 2016

Construction

Start Date: June 2016
Projected Completion Date: June 2018
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $2,107,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017