Playground 52 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will reconstruct the play equipment, safety surface, spray shower, fence and landscaping at Playground 52.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $3,973,000
Funding Source: Mayoral

Location

Playground 52 LII, Bronx
Kelly Street Between Avenue Saint John and Leggett Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018