St. Mary's Park Playground West Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    44% complete

This project will reconstruct the basketball and tennis courts, and install play equipment, seating areas, planting beds and trees at St. Mary's Park Playground West.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $2,912,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

St. Mary's Park , Bronx
St Anns Ave, East 149 St and St Mary's Recreation Center

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/12/2018