Corlears Hook Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    10% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $2,777,000
Funding Sources:
  • Mayoral
  • Federal

Location

Corlears Hook Park , Manhattan
Cherry Street between Jackson Street and FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project