Corlears Hook Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019
Adjusted Completion Date: November 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Federal

Location

Corlears Hook Park , Manhattan
Cherry Street between Jackson Street and FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/22/2019