Corlears Hook Park Comfort Station Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Adjusted Completion Date: June 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Corlears Hook Park , Manhattan
Cherry Street between Jackson Street and FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/25/2018