Corlears Hook Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    3% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $2,777,000
Funding Sources:
  • Mayoral
  • Federal

Location

Corlears Hook Park , Manhattan
Cherry Street between Jackson Street and FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/15/2019