Corlears Hook Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Corlears Hook Park, Manhattan
397 FDR Drive at Cherry Street between Jackson Street and the FDR Drive, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2017