Corlears Hook Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Corlears Hook Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: April 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Corlears Hook Park , Manhattan
Cherry Street between Jackson Street and FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/22/2019