Hunts Point Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    39% complete

This project will reconstruct the play equipment, safety surfacing, spray shower, fencing, benches and landscaping in Hunts Point Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: January 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: August 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $3,123,000
Funding Source: Mayoral

Location

Hunts Point Playground, Bronx
Spofford Avenue Between Faile Street and Hunts Point Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018