Hunts Point Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    78% complete

This project will reconstruct the play equipment, safety surfacing, spray shower, fencing, benches and landscaping in Hunts Point Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: January 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: August 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $3,123,000
Funding Source: Mayoral

Location

Hunts Point Playground , Bronx
Spofford Avenue Between Faile Street and Hunts Point Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2018