Conch Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Conch (PS.105) Playground.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: October 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: January 2018

Understand how we build parks.

Funding

Total Funding: $6,657,000
Funding Source: Mayoral

Location

Conch Playground , Queens
Located at Beach Channel Drive between Beach 49th Street and Beach 51st Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/23/2018