Van Alst Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Van Alst Playground.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: November 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: October 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $3,319,000
Funding Source: Mayoral

Location

Van Alst Playground, Queens
29th and 30th Avenues between 14th to 21st Street in the borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/14/2017