Sol Lain Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entire playground including play equipment, spray shower, basketball court, multi-purpose play area, benches, fences, drainage, water supply, security lighting, sports lighting and landscaping.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: October 2017
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $3,116,000
Funding Source: Mayoral

Location

Sol Lain Plgd , Manhattan
Adjacent to P.S. 134 between Henry Street and East Broadway

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/15/2019