Sol Lain Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the entire playground including play equipment, spray shower, basketball court, multi-purpose play area, benches, fences, drainage, water supply, security lighting, sports lighting and landscaping.
Project Timeline
Design
Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
July 2016
Construction
Start Date: August 2016
Projected Completion Date:
October 2017
Completion
Date:
September 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Sol Lain Plgd
, Manhattan
Adjacent to P.S. 134 between Henry Street and East Broadway
Project Staff
Project Liaison: Steve Simon