Louis Simeone Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    63% complete

This project will construct new pavements, drainage, benches, game tables, fencing, fitness equipment and planting at Louis Simeone Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: September 2016

Construction

Start Date: October 2016
Projected Completion Date: January 2018

Understand how we build parks.

Funding

Total Funding: $2,557,000
Funding Sources:
  • Mayoral
  • City Council

Location

Simeone Park, Queens
Bounded by 101 Street, Lewis, Strong and Radcliff Avenues in the Borough of Queens.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017