James Weldon Johnson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, active recreation and joint operated playground with the adjacent school.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: September 2016

Construction

Start Date: November 2016
Projected Completion Date: February 2018
Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $4,789,000
Funding Source: Mayoral

Location

James Weldon Johnson Playground , Manhattan
South of 115th Street, Between Third Avenue and Lexington Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/11/2018