Grassmere Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, swings, landscaping, and sitting areas in Grassmere Playground.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $3,331,000
Funding Source: Mayoral

Location

Grassmere Playground , Queens
This project is located East of Hanson Court, between Grassmere Terrace and Briar Place, in the Borough of Queens.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2018