Levy Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Levy Playground with a new basketball court, play equipment, safety surfacing, interactive water features and landscaping.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: November 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $2,078,000
Funding Source: Mayoral

Location

Levy Playground , Staten Island
Jewett Avenue and Castleton Avenue

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 07/19/2018