NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Hunts Point, Playground 52, Carmansville, MLK, and Sol Lain Playgrounds Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    73% complete

This project will reconstruct comfort stations in various locations in the Bronx and Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $6,226,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?