Hunts Point, Playground 52, Carmansville, MLK, and Sol Lain Playgrounds Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    99% complete

This project will reconstruct comfort stations in various locations in the Bronx and Manhattan.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: January 2018
Adjusted Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $6,226,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 10/15/2018