Arrochar Playground and Grandview Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    61% complete

This project will reconstruct the comfort stations at various locations in Staten Island.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: January 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: April 2017

Construction

Start Date: July 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $2,527,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 02/16/2018