Arrochar Playground and Grandview Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort stations at Arrochar Playground and Grandview Playground.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: January 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: April 2017

Construction

Start Date: July 2017
Projected Completion Date: October 2018
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $2,527,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 07/19/2019