Lincoln Terrace Park Field House Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will demolish the existing comfort station and construct a new field house in Lincoln Terrace Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Adjusted Completion Date: July 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Lincoln Terrace / Arthur S. Somers Park , Brooklyn
Buffalo Avenue between Eastern Parkway and East New York Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/27/2022