Lincoln Terrace Park Field House Construction
-
100% complete
-
60% complete
-
0% complete
This project will demolish the existing comfort station and construct a new field house in Lincoln Terrace Park.
Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.
Project Timeline
Design
Start Date: April 2015
Projected Completion Date:
January 2016
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Adjusted Completion
Date:
July 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Lincoln Terrace / Arthur S. Somers Park
, Brooklyn
Buffalo Avenue between Eastern Parkway and East New York Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 06/27/2022