Jesse Owens, Stockton and Stroud Playgrounds Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort stations Jesse Owens Playground, Stockton Playground, and Stroud Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: December 2018
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $1,252,000
Funding Source: Mayoral