West Playground Comfort Station Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a comfort station in West Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

West Playground , Brooklyn
Avenue Z between West 1st Street and West Street

 

Project Staff

Project Liaison: Davey Ives