Bowne Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, asphalt field, seating area and swings at Bowne Playground.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: January 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: July 2017

Construction

Start Date: August 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $4,767,000
Funding Source: Mayoral