Astoria Heights and Bowne Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    78% complete

This project will reconstruct the comfort stations at Astoria Heights Playground and Bowne Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: January 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Construction

Start Date: February 2017
Projected Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $3,375,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/24/2018