Luther Gulick, Lyons Square, Saw Mill, Melrose Commons and Ten Eyck Playgrounds Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    48% complete

This project will construct comfort stations at various locations in Brooklyn, the Bronx, and Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Construction

Start Date: February 2017
Projected Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $14,736,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 12/08/2017