Luther Gulick and Yolanda Garcia Parks, and Lyons Square, Saw Mill, and Ten Eyck Playgrounds Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will construct comfort stations at Yolanda Garcia Park, Lyons Square Playground, and Saw Mill Playground in the Bronx; Ten Eyck Playground in Brooklyn; and Luther Gulick Park in Manhattan, and reconstruct Saw Mill Playground with a basketball court, track and synthetic turf field, fitness and play equipment, and a spray shower.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Construction

Start Date: February 2017
Projected Completion Date: August 2018
Adjusted Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $20,309,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 08/12/2020