Astoria Heights-JHS10 Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Astoria Heights Playground.
Project Timeline
Design
Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date:
February 2016
Procurement
Start Date: February 2016
Projected Completion Date:
October 2016
Completion
Date:
September 2016
Construction
Start Date: November 2016
Projected Completion Date:
May 2018
Completion
Date:
May 2018
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Astoria Heights Playground
, Queens
30th Road between 45th and 46th Streets
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/15/2021