Marine Park Salt Marsh Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: April 2020
Completion Date: April 2021

Construction

Start Date: September 2021
Projected Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Source: Mayoral

Location

Marine Park , Brooklyn
Avenue U and East 33rd Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/20/2022

Was this information helpful?