Marine Park Salt Marsh Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Marine Park , Brooklyn
Avenue U and East 33rd Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/22/2018