Marine Park Salt Marsh Nature Center Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
April 2020
Adjusted Completion
Date:
December 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Marine Park
, Brooklyn
Avenue U and East 33rd Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/26/2021