New York State Pavilion Observation Towers Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Flushing Meadows Corona Park, Queens
Perimeter Road and United Nations Avenue South

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017