Brooklyn General Site Work (BG-311M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct play equipment, safety surfacing, handball courts, basketball courts, pavements, fencing, plantings and general site work at various Brooklyn locations.

Project Timeline

Design

Start Date: February 2011
Projected Completion Date: March 2011
Completion Date: March 2011

Procurement

Start Date: March 2011
Projected Completion Date: December 2011
Completion Date: April 2012

Construction

Start Date: June 2012
Projected Completion Date: June 2014
Completion Date: December 2014

Understand how we build parks.

Funding

Total Funding: $828,000
Funding Source: Mayoral