NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

East River Esplanade Stabilization and Reconstruction, East 60th-125th Streets

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will stabilize or reconstruct critical portions of the East River Esplanade, including seawalls, bulkheads, platforms, and other waterfront structures.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: October 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/23/2018

Was this information helpful?